No Actual Cost against Manual Task Confirmation in cProject?

93 Views

Dear PPM Gurus,

I am doing a Manual confirmation (not CATS confirmation) on cproject Task. It is happening successfully and I am getting "Work Complete %" on the Task Dashboard. However, I do not see 'Actual Costs' being populated against this confirmation on ECC side or on cProject Dashboard.

Is it that the manual confirmations are not expected to bring the actual costs as a standard system behavior? If so, how come confirmation
via CATS brings actual costs on cProject Dashboard (after running CATS xFer & program 'DPR_CATS_CPR_TRANSF')?

So ‘Manual Confirmation’ & ‘CATS Confirmation’ is treated differently in cPropject or am I missing something here?

Your inputs will be appreciated. I am on PPM 5.0 with ECC EhP 6.