Skip to Content
0
Former Member
May 03, 2013 at 09:15 AM

How to update replinishment indicator in spp side?

45 Views

This RICEF will
change two programs, one on ECC side and one on SPP side. The code changes will
be specific to plant (4860) and will achieve the following:

  1. Manual
    updated made on ECC side to Safety Stock, Reorder Point, Service Level and
    ABC Class fields on ECC side will not be transferred to SPP.

2. Changes
made to cross plant material status or MRP type in material master on ECC
side will automatically influence the updates to replenishment indicator
and DRP lock dates fields in SPP product master.

Test condition:











In ECC update cross plant material
status in material master purchasing view to Y1 or Y2



This
should either change the replenishment indicator in product master to NN or
update the DRP Lock dates.





Use material 65.03901-0075 and plant 4860




In ECC update cross plant material
status in material master purchasing view to blank



This
should either change the replenishment indicator in product master to blank
as well as update the DRP Lock dates to blank.





Use material 65.03901-0075 and plant 4860