Experts: When using COHV to mass processing production order, how can revoke the technical completion?

There is a survey in 2008 saying that there is no transaction for this to be done in mass, one should be created LSMW.

Currently there has been no update possible?

Best Regards.,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

There is still no mass processing available in SAP standard for unsetting the status TECO in order. This can only be done in CO02 / COR2

BR Sabine

former_member242092
Active Participant
0 Kudos

Hi,

Create a BDC recording and have a program of CO02 to revoke the production order.

Regards,

RP Jaiswal