May 01, 2013 at 12:16 PM

WCM - Permits can be issue in two control rooms

37 Views

Hello experts,

I have a little challenge or problem that you maybe can give me a little feedback on.

The issue is that we on some plants have two control rooms that must be able to issue PTW.

One control room is taking care of Permits on primary components on the Power Plant and the other is taking care of Permits for work carried out on harbour and fuel handling department.

We cannot uniquely in all cases specify on the functional location whether it is one or the other control room that have to issue the work permits - so this is a decision taken by the scheduler.

How can we do this - any good idea?