Hi,

During heuristic run in APO, Purchase requisition is created with the default scheduling mode backward and forward.

how to setup customization that, purchase requisition should consider only backward scheduling and allow

purchase requisition release date to be set in the past if needed.

Any thoughts how to achieve this?

Thanks,

Krish

Accepted Solutions (0)

Answers (1)

Answers (1)

dev_shetty
Active Participant
0 Kudos

Hi Krish,

                You can not release for the past. This is like dead man saying " I will have yesterday lunch today that I didn't have". If you don't run SNP heurisitc on that day or several days  the future releases automatically become past as day pass. One more thought is "confirm or fix" PReqs so that heurisitc will not modify them.Try this let me know if it works.

Thanks