Former Member
Apr 24, 2013 at 02:04 PM

Error message in QA01

326 Views

Dear all,

When we create an inspection lot manually (Trx. QA01) and maintain inspection start date / end date in such a way that they fall during weekends/holidays, then system gives a warning message saying "The start /end date of the inspection is not a valid workday".

But in our system for only one user this same message is appearing as error message. Because of this, the user is unable to maintain proper dates for some lots.

I checked the factory calendar assignments for different plants/users, it is all same.

We also copied the user details(for which error appear) from production server to development server and analyzed, but surprisingly in the development server, the same user is getting only warning messages!!!

Can anyone share their knowledge why system is behaving like this.

Regards,

Pavan