How travel management is integrated with the OM and PA?

Regards,

Vijay

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 30, 2013 at 06:59 PM

    I could think IT0017 is the Key for Travel Management, which is PA infotype.

    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/FITVPLAN/FITVGENERIC.pdf

    This would help you all the way.

    Warm Regards!

    -Kanuku

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 30, 2013 at 09:48 PM

    It also requires an active and valid at system date IT0000 and IT0001 as well as the travel infotype (IT0017 as mentioned) whilst cost center can be defined in either IT0001/IT017/IT0027 and Travel also checks payroll integration during settlement process and posting to FI (a dummy payroll record will suffice if no payroll integration is required)

    I moved this to the Travel Management forum also but please do check out the external wiki and SAP help as this is explained in more detail

    http://wiki.sdn.sap.com/wiki/x/EwBIBQ

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.