Work Schedules

0 Kudos

Experts,

Not sure, if this is the right place to post the question.

Currently we have implementation with Work Schedules having Begin & End Time. We would like to implement Work Schedules without  Begin & End Time, that is, just duration based. Wondering, if any of you have any experience with similar situation.

Thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

siddharthrajora
Product and Topic Expert
Product and Topic Expert
0 Kudos

yes in V_T550A, you can define something called flextime, it doesn't have to be planned working time all the time., you can have it without hours