Former Member
0 Kudos

Hi Friends,

Please bear with me, if this is a basic question.

How to make confirmed qty as 100.

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

How to make confirmed qty as 100

You cannot key in manually this column.  System will automatically fetch whatever stock is made available to the extent of order quantity.  In your case, if it is not happening, then check in MMBE itself by dragging to right side where you can see "Schedule for delivery".  Whatever quantity you see in unrestricted is inclusive of this column.  Alternatively, you can also check in MD04 where you can see the delivery reference against which stock would have reserved. 

G. Lakshmipathi

Former Member
0 Kudos

Dear Lakshmipathi,

Thanks and it is because of Factory calender not assigned in Plant level.

Have understand this from MD04 error msg.

However have already seen this while creating SO in VA01, as a warning msg.

Since, it is warning msg , we didn't give importance.

Now the issue resolved !!!

Thanks once again.

Answers (6)

Answers (6)

jpfriends079
Active Contributor
0 Kudos

Hello Navaneetha,

In my opinion, TCode MMBE may not be able to give a prefect picture to your stock level.

Try TCode co09 to check availability overview, where you provide

- Material

- Plant

- Checking Rule

This would provide you accurate stock levels for the material through "Cumulative ATP qty" for Stock.

Thanks, JP

0 Kudos

Do you want to delivery only quantity 100 for every delivery? If yes, you have to input order quantity as 100 and maintain delivery unit as 100 at material master record.

Former Member
0 Kudos

Dear Siva,

It is not like that and the delivery quantity depends on customer requirement.

Shiva_Ram
Active Contributor
0 Kudos

There may be more than one reason for system not confirming quantities at schedule line level. Check the status of the order, to see whether credit block has been applied or not. If applied then in VKM1/VKM3, release the order and check again.

Regards,

0 Kudos

If I understand you correctly, you want to deliver only in confirmations of 100. right? If this is the case, you need to enter order quantity as 100 and delivery unit as 100 in material master record . The confirmations to the line item depends on many factors like stock availability, delivery unit, scope of check etc... So in standard SAP is not possible to keep 100 as confirmation unless modification.

WR,

Siva B

siva_vasireddy2
Active Contributor
0 Kudos

Hi,

  plz confirm whether this is a Returnable Packing material.

Former Member
0 Kudos

Hi Siva,

No. This is a Returnable Packing material.

former_member204407
Active Contributor
0 Kudos

Hi ,

please check if you maintain anything in MRP1 and MRP3 Tabs in Material Master -VELVAS1

1. MRP type in MRP1 Tab-maintain with ND-No planning

2.Strategy Group in MRP3 Tab with Blank in Material master

save it and create sales order.

Regards,

Krishna.

Former Member
0 Kudos

Hi Kumar,

Have not maintained any MRP views for this materil.

Plz assist.

former_member186385
Active Contributor
0 Kudos

Hi,

Select the Item and goto

Environment-->availability

and check the stock

if the stock is available, then carry out availability to confirm the stock

if possible please put the screenshot of availability check

regards,

santosh

Former Member
0 Kudos

Hi,

Have checked but nothing has happen on the screen.