Kindly let me know if there is any Standard table or FM through which we can get the Project Closing date.

Thanks,

K.Kiran.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jan 09, 2017 at 02:57 PM

    Either look in table JCDS for date when the closed status was applied or use a FM like STATUS_READ_MULTI.

    Regards,
    Raymond

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 10, 2017 at 11:23 AM

    Raymond,

    Thanks for providing the info

    From PROJ table I got the OBJNR and got the statuses from JCDS table.Out of following Closed status' which one should we be considering to determine whether a Project is Closed or not.Kindly let me know if there is any table to get the Closing date.

    I0046

    I0135

    I0452

    I2510

    I7102

    IFO07

    Regards,

    K.Kiran.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 10, 2017 at 12:29 PM

    Raymond,should the UDATE of JCDS be considered as Closing date.