Project Closing Date - PS Module

Jan 09, 2017 at 12:34 PM

147

avatar image

Folks,

Sub :- PS Module

Kindly let me know if there is any Standard table or FM through which we can get the Project Closing date.

Thanks,

K.Kiran.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Raymond Giuseppi
Jan 09, 2017 at 02:57 PM
0

Either look in table JCDS for date when the closed status was applied or use a FM like STATUS_READ_MULTI.

Regards,
Raymond

Share
10 |10000 characters needed characters left characters exceeded
Kiran K Jan 10, 2017 at 11:23 AM
0

Raymond,

Thanks for providing the info

From PROJ table I got the OBJNR and got the statuses from JCDS table.Out of following Closed status' which one should we be considering to determine whether a Project is Closed or not.Kindly let me know if there is any table to get the Closing date.

I0046

I0135

I0452

I2510

I7102

IFO07

Regards,

K.Kiran.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

The first one I0046...

0
Kiran K Jan 10, 2017 at 12:29 PM
0

Raymond,should the UDATE of JCDS be considered as Closing date.

Isn't there any table to get the Closing date.

K.Kiran.