Help with the data flow

Former Member
0 Kudos

I have to feed 2 infoobjects master data from one data source.  for example: IOBJ1 and IOBJ 2 from DS1.  so if i first rn the infopackage for DS1 and bring data into psa and then run iobj1's Dtp, that request will be marked for green and IOBJ2 will get 0 records. i am in 7.3 system, how can i achieve this requirement? please help. thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

One last question, in my process chain should i do it in this sequence?

Infopackage to get the data into PSA for DS1

DTP to IOBJ1

DTP to IOBJ2

?

and the datasource is DELTA-ENABLED.

Thanks.

RamanKorrapati
Active Contributor
0 Kudos

Hi Venkat,

its right way. you can go ahead.

1. Infopackage to get the data into PSA for DS1

2.  DTP to IOBJ1,

3. DTP to IOBJ2

4. You can add ACR(attribute change run) from both objects.

Thanks

ravi_chandra3
Active Contributor
0 Kudos

Hi

Yes, u are correct. but make sure that in the PC, finally add the attribute change run process type.

Former Member
0 Kudos

Hi,

Once the data is there in PSA level , you can use this data to load to any number of info provider .

What you are doing is correct , both the object should get loaded once you will run the DTP .

and also in in PC the only thing you have to see that before running any of those 2 DTP , PSA should get loaded that is all . So your PC also should work fine.

Regards,

Neha.

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi Venkat,

Try running both dtp's in full update mode if the source is not delta enabled. But make sure you delete the PSA requests everytime after the loads.

Regards,

Blasco

former_member182869
Participant
0 Kudos

Hi venkat,

You can load the data two Objects from Data source, but keep in mind both Info packages should not run parallel  . complete one run then run 2nd one once complete 1st one.if you do it parallel then it will show Green with 0 records

Regards

Sree

RamanKorrapati
Active Contributor
0 Kudos

Hi Venkat,

Start triggering DTP to IOBJ2 and let's see, you will get data.

Thanks

ravi_chandra3
Active Contributor
0 Kudos

Hi venkat,

If you run the DTP1 to move the records to the IOBJ1  then the request status will set to green for that particular data target but not to the IOBJ2 data target.

Hope u got it,

Former Member
0 Kudos

Venkat,

Do you want to connect 2 master data info-objects to 1 data source?

You just need to run 1 IP and 2 DTP.

I couldn't understand why you want to get 0 records to your 2 nd info-object?

Correct me if my understanding is wrong.

Regards,

Venkatesh