Dear experts,
i have a production order which contains 3 operations say 0010,0020,0030. my requirement is that 0030 operation should be started after 12 hours from 0020 production starts. i had maintained quee time of 12 hours in operation 0030.but the operation start time of 0030 is calculating from the operation end time of 0020 .if i am maintaining OVERLAPPING SYSTEM IS NOT CONSIDERING THE QUEE TIME
my process is running like this
operation start time operation end time
operation 0020 12/4/13 08.30.00 12/4/13 22.45.00
operation 0030 12/4/13 20.30.00 13/4/13 02.30.00
system is calculating like this
operation start time operation end time
operation 0020 12/4/13 08.30.00 12/4/13 22.45.00
operation 0030 13/4/13 10.45.00 13/4/13 16.30.00
Thanks,
hari krishna