I have one doubt.   which price controll(S or V) to be maintain  when Material leadger is active.  Please guide me.

Thanks and Regards

Tulli

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

set up with S

Former Member
0 Kudos

I would also recommend using price control S for raw materials when actual costing for finished goods is used.

The reasoning is the following: actual costing for finished goods is a "period average" concept.

When using price control V, those period averages are calculated with raw material prices that vary during the period, while using S for raw materials also averages the cost of raw materials during the period. This seems a more consistent concept to me.

Moreover, price control V can result in very strange behaviour of the moving average price, especially when errors in the price of purchase orders are involved (oops, entered 100$ per Kg instead of 100$ per ton). This may result in very incosistent actual costs for different finished goods using the same raw materials. Price control S ensures much more robust realistic periodic values for raw material costs.

Regards