planned order created in the period without capacity ressource

Please all

The MRP created automatically the planned order in the period there is no capacity ressource. I do not understand. The calendar is open at that period but there is no ressource available. I want to know how to manage. I maintained the capacity of ressource to 0% in that defined period, but the planed order are proposed in that period by MRP

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 09, 2017 at 11:19 AM

    Hello

    The planned order basic dates are always calculated according to the plant factory calendar. The resource calendar is only used to calculate the opration dates during lead time scheduling.


    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 10, 2017 at 05:50 AM

    Hello Prosper,

    Could you check in the material master, MDM is maintained Re-order point @ MRP-1 or safety stock @ MRP-2.

    Best Regards

    Venkat