on 04-05-2013 3:44 PM
Hello,
We are a Engineering company
Our Pricing procedure is
Basic
+ Excise Duty
+ Edu. Cess
+ H.Edu. Cess
Sub Total
+ CST / VAT
Sub Total
+ Transportation
Grand Total
Now we want to implement Milestone billing as our billing pattern is such.
10% Advance on Basic Price
10% Against drawing approval from Customer on Basic Price
70% + All Taxes against Material Despatch from Factory
10% After one year of product supply.
Now tell me how can i Configure this scenario in SAP.
As at present I have configured milestones billing but it is calculating advance on Basic + Taxes instead of Basic only.
Please guide
Best Regards,
Vishal Kadia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vishal,
Please check what is the step no you are using to calculate 10% advance. Ensure that you are calculating on Base price step. Moreover, see if you have assigned any routines for 10% advaces step condition.
It would be easy if provide your PP screenshot.
Regards, Sai Krishna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.