How to update Composite-Test in CBTA

Hello all,

I create several test scripts, from which a Composite-Test was created. I've noticed that if I later customize a test script in CBTA, its old and not the new version will continue to be used in the test composition. Does anyone know how to update the Composite-Test after the change of their components?I create several test scripts, from which a Composite-Test was created. I've noticed that if I later customize a test script in CBTA, its old and not the new version will continue to be used in the test composition. Does anyone know how to update the Composite-Test after the change of their components?

Thanks for your answers

Alena K

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 04, 2017 at 10:33 AM

    Hi Alena,

    After customizing your test script just refresh the composite script and it will take all the changes that you made.

    I dont think there is any other way to update you composite scripts. Please share if you have found any alternatives.