Skip to Content

Production Order not possible without Standard Cost Estimation

Hello,

For a Material with Valuation type "S"- Standard Valuation, which is without a standard cost estimation, for this material No Production Orders Should be created. Kindly help me, how to configure for this requirement, So that User cannot create a Production order for a material which doesnt have a Valid Standard Cost estimate.

Kindly provide your valuable suggestions

J.Balakrishnan

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 04, 2013 at 03:57 AM

    Hi J.B,

    By using this user exit PPCO0001 like,

    Period of Current Standard Cost Estimate: MBEW -PPRDL is '0" or

    Fiscal Year of Current Standard Cost Estimate: MBEW - PDATL is empty which will not allow the user to create production order without any standard cost estimate.

    When standard cost estimate is not done it will stop the user to create production order and display the message as cost estimate is to be done for this material. This is will solve your problem.

    Please test and revert.

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 03, 2013 at 11:19 AM

    Hi,

    Kindly run Tcode CK40N for the material for which you are trying to create PO.

    Complete costing run till release .

    Then no error will come.

    Try & let me know,if any issue

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 03, 2013 at 12:10 PM

    Dear Balakrishna,

    For your requirement you can maintain release authorization, so somebody can monitor or

    In confirmation parameters (opk4) maintain check as termination of incorrect actual costs, so that system will not allow user to do confirmation postings, check costing run (ck11n) again, bring back the production order in release stage (Read PP master data), then do cost order (from release flag to third button), release the production order and try again confirmations and postings.

    Check and revert me back.

    Pradeep.M

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.