Dear All,
I want to firm planned orders firm generated during Auto MRP .
Kindly let me now the setting for the same,Including SPRO,Master data etc
Warm Regards,
Hi Sunil,
If you want to firm order for next one, two, three etc days, you can planning time fence field in material master MRP 1 view.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you use MRP typeFixing then the planned orders will be automatically firmed during the MRP Run.
CSN