Dear All,

I want to firm planned orders firm generated during Auto MRP .

Kindly let me now the setting for the same,Including SPRO,Master data etc

Warm Regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member1362664
Contributor
0 Kudos

Hi Sunil,

If you want to firm order for next one, two, three etc days, you can planning time fence field in material master MRP 1 view.

Thanks

Former Member
0 Kudos

Hi,

If you use MRP typeFixing then the planned orders will be automatically firmed during the MRP Run.

CSN

Former Member
0 Kudos

I have tried MRP type P1 & planning time fence 3 days but still planned orders are not firming .

Any other settings ?