Dear Experts,

Can anyone guide where can i get the bifurcation of cost in PM orders for below sinario.

i created order with some components in it of say Rs. 100/- on 01.03.2013. Due to some requirement in same order i change & include another component of say Rs. 100/-. Now in Actual cost in order it shows Rs. 200. & in control tab it shows the changed by & changed date.

My requirement is where will i get this two different costs of order according to created date & changed date.

We have generated a report to get cost of materials & services of different plants on one sheet along with respective GLs. We are unable to divide the actual cost of order to created amt & changed amt.

Plz advice.

Regards,

Harish