on 03-17-2013 6:41 AM
Dear Experts,
In our company Data flow Architecture is ECC 6.0 to BW 7.0 to BPC 7.0 and BO 3.1 ,
Now we are planning to upgrade BW 7.0 to BW 7.3 and we dont want to upgrade BPC.
My doubt is if we upgrade BW System 7.0 to 7.3 any problem in BPC system .
and what are the ways to approach to upgrade BW system without affecting any problem in BPC system.
please suggest to me , How to approach, Thank you,
Thanks & Regard's
Rajasekhar
Hi Raja,
Please better to post this doubt into BPC forum not in bw.
http://scn.sap.com/community/epm/planning-and-consolidation-for-netweaver
As my guess it won't be problem. bcaz while pulling data from BW to BPC, we are just passing info object values(in dimensions) only.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi raja,
After the upgrade info cubes may go in active in CPMB space.
Please look at below notes might be useful.
SAP Note 1390477 Additional info for upgrade to SAP NetWeaver 7.3
SAP Note 1636053 - Upgrade to SAP NetWeaver 7.30: BW server: Useful note
SAP Note 1636057 - Upgrade to SAP NetWeaver 7.30: BI Java: Useful note
http://scn.sap.com/thread/3171991
http://scn.sap.com/docs/DOC-12042
Thanks