    hello gurus,

                          

i got a requirement from the end user like this.

actually he created a corrective maintenance order with components in it.

and he did a mistake in the cost center.

as that the reservation is created for the component..is there any possibility to reverse the process to change the cost center?

and even i need to assign the components to the cost center for which am going to change

the current status of order is........REL,MENC,PRC,SETC.

pls guide me to achieve it..

thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

If Reservation has been created against order, where do you want to change the Cost center??

Only while settlement, cost will be settled to cost center, if cost center has been assigned as settlement receiver.

former_member248088
Participant
0 Kudos

can i change the cost center in settlement rule in the order?

Former Member
0 Kudos

Yes, you can change the cost center in settlement receiver.