Price defaulting for services in PO

The end-user has several prices for similar type of service but only one service master record is maintained.

The end-user does not want to maintain different service master records as it'd be tedious process now.

The problem is:

PR is created with the same service number but different prices are quoted.

When converting this PR into PO, the price from the first line item is defaulted for all line items with same service number.

How to solve this issue so that the price comes from each line of PR into each line of PO ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Mar 13, 2013 at 05:32 AM

    Hi,


    If you already created a service PR and want to have a service PO from service PR with defaulted price for each service lines,then create functional authorization for buyer as ZU ,choose adopt PO price and select check box of "Ref. to Purchase Requisition" in t.code:OMET & assign the value ZU with parameter ID EFB with users & save.

    Now create a service PO from service PR and the difference.

    NOTE:

    For automatic price for service master during creation of PR , user can have condition record in t.code: ML45 with service condition type.

    Refer a thread which alreday discussed-how to picks price from PR to PO

    https://scn.sap.com/thread/1908600

    Regards,

    Biju K

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 08, 2014 at 05:30 PM
    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 09, 2014 at 05:33 AM

    Hi,

    Pls check again it's not possible becuse when we used same service number but different price are quoted. and when converting PR into PO, System will be picked same service no. with different price.

    and Service po with referance same pr no.


    Service pr.PNG (42.4 kB)
    Service po.PNG (59.2 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 09, 2014 at 07:00 AM

    I request you to read the OSS note 438718 mentioned by Luis Eduardo Cabral da Silva

    It explains the SAP design, and SAP clearly states that 2 service master should be created as most programs do not check if different conditions are maintained.

    If you get a good result, then this is just by chance.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.