Hi Guru,

Scenario : create PR with account assignment Q convert in PO with same account assignment then MIGO after migo check stock in MMBE stock showing project stock but why not showing in MBBS project stock report what is the reason.

i have checked with se16n with table MSPR, MSSQ and more relevance table as EKPO-SOBKZ and Number of Material Document (MBLNR) then you can get SOBKZ from MSEG table

Regards,

Aryan

Accepted Solutions (0)

Answers (2)

Answers (2)

AmalaSrinivasa
Active Contributor
0 Kudos

Dear Arya,

Please check the same in MB51, by giving the special stock tick and along with special stock indicator.

R,

Amal

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

HI ,

Please check your Project, T.code CJ20N, in Control Tab, Project stock.its should be Valuated Stock.

Former Member
0 Kudos

ya srinivas its valuated stock and also tick mark in project profile as valuated stock.

such in cj20n in control tab how to know valuated material or non valuated material?