Tables to get earned value details

Hi All,

I am trying to get table details for getting the earned value (BCWS, BCWP, EAC) data apart from RPSCO table. I would need to report earned value details in Controlling area currency and in object currency.

Can anyone help me in this regard.

thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Mar 08, 2013 at 12:15 PM

    Hi,

    Check Table RPSQT.

    Check reports CNE1,CNE2,CNE5.

    Also for report refer Note 503246 - Check report for the earned value analysis

    Check if it can help you.

    Regards

    Tushar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello,

      Yes you are right you also need check COSB. The costs origin are entered in COSP and COSS but during the RA process the systen can check how you recognize you monthly  revenues and the adjustment is stored in COSB, but here you only have costs/ revenues adjusted during RA process.

      Then you need to check the 3 tables.

      Regards