RE: procurement of spare through WBS in sap ps

Dear ps experts,

all machinery suppliers we are procuring 3 years spares.As on date we raised regular indent through system

but this spares will be utilize in future not now.

How this will come in inventory of plant (project) & how to capitalize ?

Please suggest us what to do in such cases

BR

prasad

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Mar 08, 2013 at 04:55 AM

    Hi Prasad

    As you are procuring spares once in 3 years, and utilised when and when required so in that case you have to procure the material to plant stock, transfer it to project stock during consumption. create sales order with respect to project ,in this way you can manage inventory and capitalize

    please check and revert back

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear Prasad,

      I hope we can follow two procedures:

      1. We can procure the material under plant stock , and later it can be transfered to project at the time of project consumption.

      2. Craete one Common Project and WBS , ( SPARES) , Try to procure all the Common materials which are related to common for all project , And this project will be carry forward by every year .

      Regards,

      vrkumar

  • Mar 08, 2013 at 04:38 AM

    if i right understood your problem then choose procurement type

    WE = Reservation plant stock

    while adding material in component overview wherein priority for plant is 1 means plant stock.

    2nd way create manual indent in ME51n with the reference of wbs for that you have to choose account assignement category as Q.

    how to capitalize = you have to create settlement profile wherein define valide reciever and settlement rule for the same.

    means lower wbs would be settle it's supperior wbs and in last depend on project type means if invesment type project then final receiver would be asset. and if customer project then PSG if copa is available or CC and more.

    Regards,

    Sanjeev

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 12, 2013 at 08:30 AM

    Hi Prasad,

    Your requirement here can be catered with Valuated Project Stock function in PS.

    First, make sure that your project is enable with "Valuated Stock" indicator in the Project Profile.

    Then, proceed with the creation of material component PR in CJ20N, use item category L, and then you will get the option to trigger PR & Reservation.

    The PR process will continue until Goods Receipt, where the costs will be posted to Inventory (Project Stock). So, your project will not bear any costs at this point.

    Until the time you want to utilize the spares, you can then do Goods Issue for the Reservation, and then costs will be posted to your project. Then, you can later settle and capitalize the costs.

    Hope this helps.

    Regards.