on 03-07-2013 10:47 PM
I have an internal order created from an appropriation request that needs to be rejected/canceled and a new request
created as a project. I have created the new project and now need to distribute the budget. How do I remove the order
from the budget dollars planning total? What Tcode do I use to get down to the order not just the position? I have tried IM22
but I get this error "60001188 has to remain assigned to a program position".
Thanks, Tonya
Hi Tonya Dahmann
planning and budgeting flow Between Investment Program and Orders/project
you can plan at order or project level and transfer to program, you cannot plan at program level and transfer it project/ order
here is below steps
1>plan the order cost or Project
2>transfer yhe plan values to investment Program IM34
3>manually increase plan values in investment program using IM35
4>Display Plan Values in investment program S_ALR_87012810
5>Budget Investment Program IM32
6>Distribute budget to order or project using IM52
7>display budget for project ch31
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.