I have a number of projects where actual costs are not reflected in the type hierarchy reports. The customazing is made for cost planning is using the currency of the transaction. Society's currency SO is MXN. Actual costs in these projects, used as the transaction currency of USD. All PS reports are configured to Use as currency SO society.

Anyone have an idea what I can do?

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Mar 07, 2013 at 06:23 PM

    Hi,

    Did you see those actual costs in CJI3 and other Cost element reports.

    What is your config settings in Create/Change Planning Profile-OPSB. Check whether you have selected Bottom Up planning and planning elements.

    If every thing is OK, execute CJEN and check again.

    Thanks,

    Sudhakar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Victor Vargas

      Hi Victor,

      If you recall my first post, whenever you encounter any descrepencies in reports, immediately execute CJEN so that it refreshes the values in respective tables and produces correctly.

      Project system having its own information system for project budget, cost plan, and network activities and WBSe etc and all the object values are getting saved in this.

       

      Sometimes it happens when you make changes in either of them, old values may leave their footprint in the database or database doesn't updated with new values. So when you run this tocode for particular project it will reconstruct the database and update the new values.

      This is what my experience with this tcode and what learnt from it.

      Also refer to the note SAP note:401192 and 52963