Former Member
Mar 07, 2013 at 08:21 AM

Transfer non-approved hours to SAP PPM

19 Views

Hi,

our client has a wish to see hours in SAP PPM as soon as they are booked, even though they are not approved yet. They run a monthly approval process so the project manager only sees the hours after a month, which is not really ideal to steer on the projects.

Does anyone have experience in SAP technical solutions for this? I know i can change the DPR_CATS_CPR_TRANS program but that might bring other problems.

Right now, we are looking at procedural changes where there will be a weekly approval process, but still that might not be ideal. Daily or twice a week reports pushed to the PM might also be an option.

Anyone here with creative ideas?