hi,

i'm creating a contract with billing plan start date 1.1.2013 till 1.12015

i've maintained cond record for PR00 For different validity periods say 

from 1.1.2013 to 31.3.2013 Price 100$

from 1.4.2013 to 31.7.2013 Price 200$

from 1.8.2013 to 1.11.2013 Price 300$ etc

now in contract Item level- billing plan tab against billing plan date i want Price Amount 100, 200, 300 $  for respective Billing dates

CAn yopu let me know how this can be achieved.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear all,

Did u find the solution about this ? i'm facing this same problem too. Is there any way we can input manual the billing value for periodic billing plan?

Lakshmipathi
Active Contributor
0 Kudos

Modify the pricing date at item level

G. Lakshmipathi

Former Member
0 Kudos

HI,

Thanks for replyin.

Is there any other way to achieve different price without changing the pricing date at item level.

i tried changing in v/06 - PR00  Setting Pricing date: as service rendered date & update - carry out new procing at item level.

But din't work.

Pls suggest if any other options.

moazzam_ali
Active Contributor
0 Kudos

Dear

Uncheck the field HeadBillPlan at item level and enter your desired amount in Bill.Value field. Please try this.

Thank$

Former Member
0 Kudos

Hi MoazzaM,

I can't see the filed HeadBillPlan.

Are you sure it's possible to change directly amount in Bill.Value field ?

Thanks a lot

moazzam_ali
Active Contributor
0 Kudos

Yes I am sure because I have done this before.

Former Member
0 Kudos

Thanks for your answer,

But the Bill.Value field is greyed out and I'm not able to change the amount.

moazzam_ali
Active Contributor
0 Kudos

Hi

Which field you are talking about? Check in below screen and update me.

Thank$

Former Member
0 Kudos

Hi,

I'm talking about Periodic billing plans and not Milestone billing plans

Thanks

moazzam_ali
Active Contributor
0 Kudos

HI

In periodic billing it is in grey mode and we can not change it. LEt me see some other way around else you have to  go with Sir Lakshami's suggestion.

Thank$