AB order acknowledgement mandatory in PO?

Dear Gurus,

The requirement is to make the AB order acknowledgement mandatory in PO?

Will it be possible in standard SAP?

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Mar 06, 2013 at 07:05 AM

    Hi,

    Set up Order acknowledgement required at the vendor level (in purchasing tab), so all purchase orders created for the vendor have the order ackowledgement reqd checked (EKPO-KZABS).

    Also, the material master must be checked with the order acknowledgement requried in the Purchasing value key in the purchsing tab.

    Hence when the PO is created the Order acknowledgement field will be checked.

    Regards,

    Shijo

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 06, 2013 at 07:15 AM

    Hello Bidhu,

    It can be maid mandatory in inforecord itself.tick Ácknowledgemnet required'... with combination of vendor and material.

    Automatically the order ack becomes activated...

    Hope this solution helps you out.

    Regards,

    Priti.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 06, 2013 at 08:01 AM

    Hello,

    In this case, you do not have to enter anything when you create a purchase order (or scheduling agreement). SAP recommends that you set the Acknowledgment requirement indicator, since you can then send out messages urging vendors to submit outstanding acknowledgments.

    If the indicator has been set in the relevant purchasing info record, it is adopted in the purchase order.

    When your vendor sends you an order acknowledgment, enter the acknowledgment number on the item detail screen. If you wish to assign the same acknowledgment number to all items, you can use the fast change facility. (Edit ® Fast change.)

    You cannot enter any dates or quantities, and are thus unable to influence materials planning. Neither can you run any analyses of confirmations.

    Use below link

    http://help.sap.com/saphelp_45b/helpdata/en/75/ee140f55c811d189900000e8322d00/content.htm

    Thanks

    Mahesh Naik

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.