Material Availability check on two storage locations

Former Member
0 Kudos

Hi experts,

Is there a way for MRP to check material availability on other storage locations aside from the one you defined as the Prod. Storage location for a component? We have a situation where the component can be sourced from two storage locations.

Accepted Solutions (1)

Accepted Solutions (1)

svs_sap
Active Contributor
0 Kudos

Hi Michael,

In configuration of availability check control in OPJJ tcode for combination of availability check you are using and rule, you can tick below option. By doing this, material availability check gets carried on for a material at the plant level and does not consider only at storage location mentioned in prod storage location field.

Regards,

Sharat

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks Sharat for the answer.

svs_sap
Active Contributor
0 Kudos

Welcome Michael. Please close the thread by marking correct answer.