on 03-05-2013 3:13 PM
Hi experts,
Is there a way for MRP to check material availability on other storage locations aside from the one you defined as the Prod. Storage location for a component? We have a situation where the component can be sourced from two storage locations.
Hi Michael,
In configuration of availability check control in OPJJ tcode for combination of availability check you are using and rule, you can tick below option. By doing this, material availability check gets carried on for a material at the plant level and does not consider only at storage location mentioned in prod storage location field.
Regards,
Sharat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Sharat for the answer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.