Material Availability check on two storage locations

Hi experts,

Is there a way for MRP to check material availability on other storage locations aside from the one you defined as the Prod. Storage location for a component? We have a situation where the component can be sourced from two storage locations.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Mar 05, 2013 at 03:23 PM

    Hi Michael,

    In configuration of availability check control in OPJJ tcode for combination of availability check you are using and rule, you can tick below option. By doing this, material availability check gets carried on for a material at the plant level and does not consider only at storage location mentioned in prod storage location field.

    Regards,

    Sharat


    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 07, 2013 at 01:59 PM

    Thanks Sharat for the answer.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.