scheduling of work orders

Our shutdown is going on, and I use IW70 for work order scheduling. At the same time I compare Primavera project with SAP PS Project. I face some problem in scheduling i.e. when I schedule work orders at the start of the day then the results of both systems are correct. But when I schedule work order in the mid of the day then SAP's results are not correct. View of both projects are attached.

Primavera View.GIF (140.1 kB)
SAP IW32 VIEW.GIF (187.1 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Mar 05, 2013 at 02:49 PM

    Hi Tanweer,

    I think it is best to ask this question in Enterprise Asset Management (EAM) space.

    Regards,

    Brendan

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 06, 2013 at 11:23 AM

    Hi Tanweer,

    You were not so explicit in what you see as incorrect in the SAP view. In the Primavera screenshot, the actual duration is 16 Hours, whilst the SAP screenshot shows planned values. It would have been interesting to show also the actual dates for the SAP operation - from the confirmation details.

    I'm not sure how Primavera derives the actual duration - but in SAP PM an operation is deemed to be continual - the actual duration measured from the earliest confirmed start to the end of the latest confirmation. Unless Primavera calculates the same way - there may well be differences. Not necessarily right and wrong - just different.

    Also be reminded that SAP will contain the most recent data entered - whilst Primavera will contain only the most recent extract from SAP and any other changes made in Primavera.

    Regards

    Andrew

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 06, 2013 at 12:58 PM

    Greetings Tanweer,

    What SAP displays in your screen are the same planned duration values as in Primavera, so there is no error there.

    To see the actual duration you need to drill down from the Order view into Operation > Actual Data > Confirmations or call up the transaction IW47 - Confirmation List

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 06, 2013 at 04:10 PM

    Could this be a system time-zone issue?

    PeteA

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.