Issue with Maintenance plan

Former Member
0 Kudos

Experts,

I have a mantenance plan created with 4 maintenance items inside it. When I choose any of the maintenance item and see 'scheduled call Items', scheduling type status field says "New start  Complete"(Sample given below).  I don't know the reason for this and never seen before. Do any one knows what could be the reason for this..??

There is some more observation on this. When i select a call number and display call item system gives up a message

"No call object exists because the relation object was inactive at call (message IP726)" ... i checked functional location and equipment both on these maintenance items and they have inactive status. Not sure whether this could be the reason but just thought of mentioning this observation... Please guide. Thanks in advance

Call Number     Plan Date     Call date     Completion date     Due package     Scheduling Type Status

1                     2013/07/20                                                  12                     New start  Complete

2                     2013/07/15                                                  12                     CyclStart  Complete

3                     2013/07/10                                                  12                     New start  Complete

4                     2014/07/05      2014/01/06                            12                     Scheduled  Hold

Regrads

J Sean

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Is it happening for any specific Equipment and / or Functional location??

If not, check the below SAP Note.

https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=321669

Former Member
0 Kudos

Hi Mahesh,

Thanks for reply. We already have this message type setup in our system. and as i mentioned in my first message, I understand that since equipment anf FL both have Inactive status, that's why i am getting this message. I mentioned this as more information for you.

I want to know why system would say 'Scheduling Type Status' field as "New start Complete" when maintenance call didnt generate any order. ???

Thanks

J Sean

Former Member
0 Kudos

Just to cross verify about other Maintenance Items, I inquired again about other equipments.

As the reference object is Inactive, system gives Call object status as New Start Complete.

Please refer the below link for the other Maintenance Call object status, out of that, this is the more appropriate status for this call object.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/3c/abb531413911d1893d0000e8323c4f/content.htm

Former Member
0 Kudos

Mahesh, Thank you very much again.

so you mean, Since there was no order created for the maintenance item, system set the status as complete ??? 

Former Member
0 Kudos

Yes, New Start Complete or Cycle Start Complete are the most appropriate status in that case. So system will set those statuses accordingly.

Answers (1)

Answers (1)

0 Kudos

Dear J Sean,

Same issue is being faced by me but i am not getting from were to see inactive status in functional location & equipment.

kindly suggest.