SETC and SETM in creating Network Activities

Hello friends,

I am trying to create a project with Network Activities. The issue is, when I am creating Activities (internal) in development system, they are getting created with SETC status (settlement rules are automatically created and hence the status SETC). But, when I am performing the same thing in test system, post creation of an Activity, it is taking me to the create settlement rule screen, wherein the settlement rule is already there with default receiver as WBS element. Hence, the status of the Activity is showing as both SETC & SETM.

Please let me know is there any idea on this behavior.

PS- I have used same Network profile for creation in both systems.

Thanks,

Regards,

Sumanth

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 07, 2013 at 07:10 PM

    Under Settlement Config there is a section "Define Settlement Rule for Network", check those settings. In particular look at "Define Strategies for Determining Settlement Rules" and make sure the strategy your are using in your network type is configured with Determination Type = 1 automatic generation and teh Default Rule is PS1.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello Ken,

      I m not copying any objects, In fact I m creating projects separately in DEV & Test systems. I am using CJ20N to create project structure.

      There is no scope of older & newer transactions as I am using same transaction in 2 different systems of same version of SAP.

      Is it something un-usual behaviour of SAP, by anyways?

      Thanks,

      Sumanth

  • author's profile photo Former Member
    Former Member
    Posted on Mar 01, 2013 at 03:46 PM

    Hi,

    Can you run this program "CNSTATUS" using SE38. This program will correct staus inconsistencies in project structure plan.

    Thanks,

    Sudhakar

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Executing the program will not have any adverse impact as you thougth. Rather it will correct the status inconsistencies if exists in the structure. First try for one project then you can go ahead with all other projects but its not required when there is no dispute noticed.

      Try suggestions given by Gokul and Tushar. Check for configuration settings. it can not go wrong with your Quality system unless small deviation from test system. try and check.

      Thanks,

      Sudhakar

  • author's profile photo Former Member
    Former Member
    Posted on Mar 04, 2013 at 09:35 AM

    Compare your settlement profile and settlement strategy configuration and assignment in both the development client and the test client. Check if there is any difference.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      HI Gokul,

      Thanks for your inputs.

      Since the project profile & network profile are same for the both the projects in different environment, I dont think so there would be any difference, but still I have checked the same and found there is NO difference among the same.

      Regards,

      Sumanth

  • author's profile photo Former Member
    Former Member
    Posted on Mar 04, 2013 at 12:13 PM

    Hi Sumanth,

    In addition to above inputs provided by Gokul & Sudhakar, please refer Note 170948 - Status inconsistency in work breakdown structure

    Check if it helps you.

    Regards

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks all for your inputs friends...

      I have checked all config settings for both projects in both systems and everything found correct, not sure where it is going wrong.

      Hence, requested global SAP support team to look into this.

      Please pass on if you find anyother useful hints.

      Regards,

      Sumanth

  • author's profile photo Former Member
    Former Member
    Posted on Mar 01, 2013 at 01:04 PM

    Hi,

    Please check settings of settlement profile for network type on testing client by using OPSC.

    If not maintain it for network type.

    Thanks.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 24, 2019 at 01:46 AM

    Sumanth, Have you got solution to this issue?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.