We are running our production server ,but due to performance issue,,,we are thinking to run database and ci on separate host.....now we are running db2 9.7 fp 5 on ecc6.0 ,,,,,,,,please suggest me on how to proceed....and i have done central instance installation lot of time .,,,but i dont know the step on how to install on the seperate server....and can we directly install db2 9.7 fp5 or first we have to install db2 9.1 with ecc6.0 then later on have to upgrade the db2 from 9.1 to 9.7...

Thanks

Rableen

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Since you are changing the Hosts, I think you can go for export and import option. I mean the system copy option. I am not sure whether splitting of hosts directly without system copy is possible. 

The procedure is as follows:

  1. Install CI in a different server.
  2. install DB 9.7 in the different server.
  3. Take an export of your existing production system.
  4. import in the  server with DB9.7 version.

Advantages

1. Your DB will be re-organized.

2.You don't need to do any DB upgrade. You can directly import the data in your desired DB version.

Thanks and Regards,

Vimal

Former Member
0 Kudos

hi Vimal,

Thanks for your reply,,,,

I did,nt install the db and ci in seperate host so can you provide me the step....

Whether i need to install java in the db server also.....and how to install db....because on central instance with sapinst we do this .....

Another thing first we have to install ci or db..