on 02-27-2013 6:01 PM
Hi All,
Normally we have 1 BOM & 1 Routing for 1 product. CK11n is used to cost the product according to this quantity structure BOM 1 & Routing 1 & then cost estimate is marked & release for a specific period. During Order costing data from BOM 1 & Routing 1 will get defaulted to PP order & accordingly order costing would be carried out.
However how is the scenarion when we work with Production version ?
Material - ABC is having BOM 1 & BOM 2, Routing 1 & Routing 2.
Production Version 1 is having BOM 1 & Routing 1. Production Version 2 is having BOM 2 & Routing 2.
Now can we have the following -
1) During standard cost estimate of ABC can I get 2 costs released for ABC as per version 1 & version 2 for the same period ? If so how to do this ?
2) During order costing BOM & Routing data will get defaulted as per the version. But in order costing GR (Plannned & Actual) is valuated ast the std price from material master. But can we this GR (planned & actual) differentially be valuated as per selected production version ? If so how to do this ?
Any clues on this would be appreciated & rewarded.
Regards,
MHP
Hi
In cas eof more than one procurement/ production method, mixed costing is to be used in which Production versions are defined in mixing ratios in T code CK94 and procurement alternatives in T code CK91.Then run standard cost extimate for production versions.
Check with your CO consultant.
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.