How Convert BADi Logics to HANA Logics - BPC 10NW on HANA

Hi All,

We have implemented BPC 10 NW for Customer.

And BADi program used for some complex calculations.

Customer implemented HANA on BW 7.31. Since BPC sits on top of BW without any migration  HANA capabilities can be used for SAP BPC 10 NW.

I came to know while reading some documents, SAP HANA will not support BADi logic at present to increase the performance of calculations ( I mean to say reduce the calculation run time, present taking 4Hrs).

To utilize the SAP HANA capabilities, calculation logic should be written on BW.

Is there any document how to convert BADi Logics into HANA logics for performance improvement?

please help

Regards,

Hari

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 27, 2013 at 05:42 AM

    Hari,

    How I understand in order to leverage HANA's processing power for logic scripts or whatever you run on the app server, BPC has to be installed directly on HANA not BW on HANA. Here is an old HANA summary page for BPC:

    http://scn.sap.com/community/epm/blog/2012/03/09/bpc-on-hana-true-innovation-without-disruption

    this is from page 21 of the NW install guide which states only reporting improvements can be accelerated:

    3.6 Installing the SAP HANA Component for Planning and Consolidation

    Follow these instructions to install the SAP HANA Component for Planning and Consolidation. This component accelerates report generation within Planning and Consolidation.

    Prerequisites

    You have applied the following SAP Notes

    1680983

    1658749

    1566845

    1654731

    Reports in Planning and Consolidation can be accelerated using the SAP HANA Component for Planning and Consolidation when they meet the following conditions:

    The storage type of the model is Periodic.

    The reports do not contain any members with formulas.

    A standard measure option in Planning and Consolidation is in use, such as Periodic, QTD, or YTD.

    Only one Planning and Consolidation cube exists under its corresponding SAP Business Warehouse multi-provider.

    Hope this helps