Issue with MPR type P2

71 Views

Hello Experts,

I'm doing scenarios with the different MRP types for demonstration of SAP possibilities to client. But I meet an issue with P2.

The SAP description (in Material Master and in customizing) is "Automatic firming without order proposal". But when I place requirements in the planning time fence the system doesn't create FIX proposals. The system is only generated proposals with exception message 56 in the MRP (shortage).

So do you already meet this issue too ? Is it a mistaken (incorrect) description ? Do you have tested this P2 MRP type and what are the results for you (fix or not fix proposals) ? Or maybe I'm wrong on the understanding of the P2 code ?

ps : I've done test with P1 and all is correct (proposals as purchase requisitions are fixed).

Thanks in advance for your advices, highlights.

BR

Marc D.