material availability not checked in PM orders

Dear Experts,

In PM orders created having components the system status shows MANC. Plz suggest how to cofigure.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • avatar image
    Former Member
    Feb 15, 2013 at 07:18 AM

    Check config node

    Plant Maintenance and Customer Service -Maintenance and Service Orders-Functions and Settings for Order Types-Availability Check for Material, PRTs, and Capacities

    Here you define scope of material availability check, In inspection control assign order type and scope for what event you want to check material availability.

    you can define scope at order create and order release.

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 15, 2013 at 07:39 AM

    There's two parts to the material availability check

    1. Order type configuration described by Yogesh above
    2. Material setting: Availability Check field on the MRP3 tab

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 15, 2013 at 09:04 AM

    Dear Yogesh / Pete,

    All above checked & maintained. But still message remains same. Plz advice

    Add comment
    10|10000 characters needed characters exceeded

    • Go to the Component tab and select each material in turn, then press the Check Material Availability button at the bottom of the screen.

      In the next screen (confirm proposal) click the Scope of Check button. this should then bring up a popup with you settings.

      Check is these settings are correct, if not, then send us a screen-shot.

      PeteA

  • avatar image
    Former Member
    Feb 15, 2013 at 11:40 AM

    Now the system status is MACA - Material committed.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 15, 2013 at 11:40 AM

    Now the system status is MACA - Material committed. I hope this is correct Answer. 

    Thanks

    Message was edited by: Harish Narayankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 16, 2013 at 11:29 AM

    Dear Experts,

    I have made changes as said by you. But i have 9 order types in each plant & 10 plants to be maintained. Can there be mass uploading of the same changes?? Plz advice.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Configurations can't be done in Mass. You have to do it as per requirement for individual combination of Plant & Order Type.