One operation in inspection plan but in PLPO table i am getting 3 operations for that product

Hi QM Experts,

Actually when i am passing PLNNR from QALS table to PLPO table, i am getting 3 operations (0010, 0020 & 0030) in it but whereas only one operation is present in the inspection plan (0030). What might be the reason, let me know please.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 06, 2017 at 10:46 PM

    Did you check to see if there is a deletion flag set on operations 0010 and 0020?