Hi ,

There is setup to get the parts from warehouse to IM through KANBAN.

when KANBAN signal triggers system create the auto Transfer order.Once transfer order is confirmed ,KANBAN bin should be changed to FULL (from red color to green color) in PK13N.

Issue : There is very long delay (12hours) in time for updating the status of the bins as FULL in the KANBAN Board - PK13N after confirmation of the Transfer order using Tcode LT12.

Please advise.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 08, 2017 at 03:09 PM

    Hello,

    Did you try refreshing the KANBAN board in PK13N ? Does that reflect the status automatically ?

    Regards,

    Ameya Beri

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 09, 2017 at 04:36 PM

    Dear Amba Prasad,

    Can you please share the setup you have made for setting up the KANBAN. I am also trying to setup the same.