issue Hardware migration of WEB AS 640 applications

Dear Experts,

Our current landscape is on SAP Netweaver 2004 , now our Datacentre is moving to new DC, hence our IM team asking us  if they take complete image of our current SAP systems and deploy into New DC machines then these applications will function normally ?

will this right move ?  insted of DB restore and Rovery ( we Basis suggeted DB system Restore).

Please find Our System Versions below

SAP SRM 4.0 , XI 3.0 and BW 3.5 along with ITS 6.20 and Requisite BugsEye and eMerge 4.0.

Please give your valuable adive as early as possible 😊

BR,

Raja.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 08, 2013 at 05:49 PM

    Hi,

       You can go either with backup/restore method provided the DB & OS version remains the same as per the  source system. If not, you can try using system export and import method.

    There is few advantages of using export and import method. Among them, you can have your DB re-organized as well as you can using the latest DB version in your target system.

    Make sure that the hostname/Ipaddress remains the same on your new DC.so that there wont be any connectivity related issues.

    We are not sure whether mirroring will work in your target system. You need to make sure that everything aspects are to be done like registery level settings are also needs to replicated same in the target system.

    So please check which step would be easier and safer for you and perform accordingly.

    I hope it helps

    Please check and provide your feedback.

    Thanks and Regards,

    Vimal

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 08, 2013 at 04:20 PM

    Hi,

    For Data center migration, recommended approach is system copy method. By this way, you can guarantee that System will work. There are lot of white papers available on it.

    Thanks

    Sunny

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Sunny,

      Thanks for your reply, Can you please tell more evaburate about System copy in DC migration, as DC maintance team is asking about Taking complete image of our Systems using Acronis True Image Eco Server and redeploy into new DC system ? so in this scenario you have any docs or sapnotes to support ? if yes please provide

      BR,

      Raja