Skip to Content
avatar image
Former Member

Message no. FMKU083:The budget amount is not sufficient for release

Dear Expert,

while carry forward the open commitment ( SC/PO ) we are getting the below error message.

FMKU083:The budget amount is not sufficient for release

Kindly check attached herewith FMJ2 error massage & FMAVCR01 budget Status


fmavcr01.png


fmj2.png

All consumable budget( 70,593,642.00)are already released at time upload the budget..

When we enter normal budget(unreleased budget) in this commitment item equal to carry carry forward open budget that time this error is not coming.

Appreciated for your reply to fix this issue

Thanks

fmavcr01.png (15.7 kB)
fmj2.png (48.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 11, 2017 at 08:47 AM

    Hi,

    Please, consult OSS note 1859520 - Budget release in BCS. Make sure that document types used in carry-forward process (I guess, you carry-over the budget with the commitment) are duly defined to work with automatic release.

    Regards,

    Eli

    Add comment
    10|10000 characters needed characters exceeded