Upload of Business Blueprint Structure in Solution Manager 7.1

Hey guys,

could anybody give advice on how to upload an excel file to create an initial Business Blueprint Structure in SOLAR01. None of the already posted threads and relpies on this matter are really helpful.

Thank you very much.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 31, 2013 at 04:09 PM

    Hi Martin,

    In solar_project_admin, after accessing the project, access the option:

    Edit -> Fill business blueprint->create template file -> structure

    All options under "create template file" will generate a file for download that you should use as reference on how to fill the information and then afterwards you should use the option:

    Edit -> Fill business blueprint-> Upload file -> ...

    to use the file you created as reference to fill the project data.

    The file generated in the first option will have examples and the possible type of data to fill.

    kind regards, Fabricius

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 31, 2013 at 04:05 PM

    Hi Martin,

    Process is simple

    1. First create a project in solman and then generate a template or excel
    2. fill this excel with your data
    3. upload it back to solution manager project

    transaction is only one SOLAR_PROJECT_ADMIN---------------Standard SAP menu option.

    If you are looking for screenshots and more details check my article here

    http://sapexperts.wispubs.com/Solution-Manager/Articles/How-to-Quickly-Create-Business-Blueprints-in-SAP-Solution-Manager-7-1-Using-Content-Upload-Interface?id=54CFB40D649341A9A428D3D08321B3FE

    hope it clarifies and help you achieve the same

    Regards

    Prakhar