cancel
Showing results for 
Search instead for 
Did you mean: 

How delivery date gets calcutaed in STO in delivery schedule tab

Former Member
0 Kudos

Hi Team,

I am bit confused on how delivery date gets calculated in delivery schedule tab of STO.

I have tried different scenarios but not able to determine how it is actually calculating date.

Does it consider planned delivery time in shipping tab or route in shipping tab.

As per my analysis i came to below conclusion:

If route scedule is active in delivery scedule tab then it gives preference only to route and not planned delivery time that is fetched from info record.

If route scedule is not active, then i am not able to determine how all dates are getting calclutaed like material staging date, GI date , GR end date and time.

Also i analyzed that if it is route sceduled then delivery date is same as GR end date, but if route scedule is inactive then delviery date will differ from GR end date.

Also GR end date and time are fields only appearing in ECC 6.0.

Could anyone please let me know how calculation taked place.

Or are there any standard notes available for calculation of delivery date in STO.

Thanks in advance for any help

Regards,

Vaibhav Gandhi

Accepted Solutions (0)

Answers (1)

Answers (1)

eduardo_hinojosa
Active Contributor
0 Kudos

Hi

See SAP Note 498143 - FAQ: Stock transfer with delivery in purchasing, question 2.

I hope this helps you

Regards

Eduardo

Former Member
0 Kudos

Hi,

Thanks for your reply.

But i am confused on how it actually calulates when route and planned delivery time are specified.

Example : route has 5 days in transit and planned delivery time is 20 days.

Then i am not able to detemine how it is calcutaing delviery date.

Everytime i get different result when i make changes to planned delivery time.

It is sure that it considers both this factors while calculating delivery date. Also everytime material availablity date changes even if quantity is same only planned delivery time is changes in the info record.

I am not sure if it is following forward scehduling or backward.

It would be very helpfull if i can get calculation system uses to calculate all dates based on route and planned delivery time.

Also for scnerios of with route schedule and without route schedule.

JL23
Active Contributor
0 Kudos

SAP tries backward scheduling first, if it determines a start date in the past  then SAP automatically switches to forward scheduling

The calculation is explained in help.sap.com

http://help.sap.com/saphelp_46c/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/content.htm

Former Member
0 Kudos

Thanks for your reply Jurgen

I have stock of material available also there available stock in MD04. Stock is 1400 KG avaialable.

I am creating STO of 200KG. I am not able to determine if it is following forward scheduling or backward scheduling. It is populating delivery date differently for different scenarios.

Also all dates like material staging dates and all dates are getting callucated automatically and differently.

Route sceduling is not active.

I created STO on 24.01.2013

When :

1)     Planned delivery time : 42 days

        Route  :  2days lead time and 21 days transit

Dates are :

Material staging : 13.02.2013     22:00

Transport plann : 12.02.2013     05 00

loading & GI        : 14.02.2013    05: 00

GR end                :  07.03.2013     00: 00

Delivery date :      07.03.2013

2)      Planned delviery time  : 7 Days

          Route same

Dates are :

Material staging : 24.01.2013      00:33

Transport plann : 24.01.2013        07: 33

loading & GI        : 28.01.2013       07 : 33
GR end                : 18.02.2013     02 : 33

Delivery date : 31.01.2013

3) Planned delivery time : 3 days

Dates are

Material staging :      24.01.2013          00:41

Transport plan   :      24.01.2013          07:41

Loading and GI date: 28.01.2013         07:41

GR End date           : 18.02.2013          02:41

Delivery date      : 28.01.2013

As you can see in all three cases delivery dates are getting calaulated differently.

I am not getting which date is getting calculated first and dependent on that other dates might be getting calculated.

Previosuly i thought that material staging date might be getting calculated first but it is also not the case. Also i thought that delviery date is GR end date always but that is also not the case.

Any help would be highly appreciated.

Thanks in advance.