Former Member
Jan 23, 2013 at 11:54 AM

Preventive maintenance order is coming before due date

116 Views

Dear Experts

There is performance based strategy plan with cycle set (250 hrs, 500 hrs,750 hrs,100hrs).

Last order release & completed on date 13.09.2012 with counter reading 2377 hrs.So next order should be generated on after 250 hrs (i.e. at 2627 hrs.).

But system has released an order after 170 hrs at counter reading 2547.

Please Guide how this issue can be overcome.

Thanks in Advance.