Dear All,

Can we configure to stop  the consumption of materials against a process order where the expiration date of the raw material batch is greater than the current date.

Regards,

ssp

Accepted Solutions (0)

Answers (1)

Answers (1)

krishna_chandra5
Active Contributor
0 Kudos

Hi,

     Follow the below links to get an idea of batch determination. In the link-1, process given is for sales order, use the same settings to do it for process order also.

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/f0caed4a-40f9-2c10-349a-96ec617a8...

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/c09b7216-65da-2b10-bdb5-870cf9916...

Revert back in case of any queries.

Regards,

Krishna Chandra

0 Kudos

Hi

Thanks for the quick reply.

How to make  relation to movement type 261 and change the mesage:

"M7667 Best before date/SLED & of batch & has been exceeded" from warning to error.

could u please tell.

regards

ssp