on 01-05-2017 11:57 PM
Hi Experts,
We are using MRP Type PD for few of the materials. When a requirement generated for any of these materials, the immediate MRP run converts it into a planned order.
My business wants to restrict the requirements to convert into planned orders if the requirement date is beyond the End of Replenishment Lead Time. Suppose a reservation requirement date is 15 days from today and the total lead time for the material (Planned Delivery Time + Processing Time) is 10 days. MRP should consider this reservation only 10 days before the requirement date. Not today.
I know Reorder Point Planning gives the above result outbox. But we can't change MRP type to ROP as we are not in a position to maintain reorder point for these materials.
With this I started looking for MRP exits to code the required logic. BADI
MD_CHANGE_MRP_DATA import and export parameters have sufficient data to make a requirement not relevant for MRP if the date is beyond end of RLT. But this BADI is triggering for MD03 transaction not for MD01. Do we have a similar BADI for MD01 to fulfill my requirement or is there a way to make use of MD_CHANGE_MRP_DATA for MD01.
Your expert opinion is highly appreciated.
Thanks
Surya