on 01-21-2013 10:27 AM
Hi,
I have created Inforecord with price date category as '2- delivery date'. And maintained different prices at different intervals.
Ex - 25/12/2012 - 28/12/2012 10 Rs
29/12/2012 - 14/01/2013 12 Rs
When i create SA on 26/12/2012 it pick's the price Rs 10. If this is the case then what is the significance of Price date category 2- Delivery date.
I have also created Delivery schedules for SA with different delivery dates.
delivery dates
1. 28/12/2012
1. 13/01/2013
Please explain me how SAP will pick the price from Inforecord when we have price date category "2". When the price date category significance will matters to the SA process.
Thanks
Mahesh
HI Mahesh,
As per PIR Prices with Date validation, Mateiral prices are Picked up in Scheduling agreement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.