in purchase requisition order type, how to assign cost center for release strategy? i.e. for different release strategy, i want to assign different cost center.
Please refer SAP note 493900.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes you can do it.
1.create one characteristic with field KOSTL for cost center with CEBAN table in CT04.
2.enter cost centers in value tab
3. assign your cost center characteristic to your class CL02
4.Enter your cost centers in release strategies --- release classification as per your requirement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Create a new Charecterstic Using Table CEBAN and KOSTL. Here Select Multiple Entries and Maintain your Values (in Values Tab Maintain all the costcenters you are making use of).
Assign it to class and Continue with your Normal Release Procedure.
Revert any issues.
Thanks,
Shiva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.